Project description
The provision of finance to the Government of Egypt (“GoE”) for the upgrade and electrification of an existing rail line connecting downtown Alexandria and north-eastern town Abou Qir (“Abou Qir line”) into a high capacity metro system.
ESIA disclosure package
1. Non-Technical Summary (NTS)
2. Stakeholder Engagement Plan
3. Environmental and Social Action Plan (ESAP)
4. Environmental and Social Impact Assessment (ESIA)
5. Resettlement Framework
Full ESIA availability
Full ESIA documentation is available at:
-
National Authority for Tunnels (NAT).
Eng. Magdy Madany
Ramses Square, Ramses Complex, NAT building - ZIP: 11794 p. B 466, Cairo
Telephone: +20225742968
Email: alexandriametro.nat@yahoo.com
-
Alexandria Governorate building:
Agricultural Road, Smouha Entrance, Alexandria
-
Misr train station, Alexandria
-
Sidi Gaber train station, Alexandria
-
Abu Qir train station, Alexandria
-
EBRD Resident Office in Cairo
EGID Building, First Floor
Block 72, off Ninety Axis
5th Settlement, New Cairo, Cairo
Egypt
Tel: 0020223225900
-
http://www.nat.gov.eg/Enviromental.aspx
- http://www.nat.gov.eg/EnviromentalAr.aspx
Enquiries
Environmental or social enquiries
National Authority for Tunnels (NAT).
Eng. Magdy Madany
Ramses Square, Ramses Complex, NAT building - ZIP: 11794 p. B 466, Cairo
Telephone: +20225742968
Email: alexandriametro.nat@yahoo.com
Web: http://www.nat.gov.eg/Enviromental.aspx | http://www.nat.gov.eg/EnviromentalAr.aspx
General enquiries
Contact Name: Ibrahim Bekheit (Head of Planning)
Email: ibna_2004@hotmail.com
Web: http://www.nat.gov.eg/Enviromental.aspx | http://www.nat.gov.eg/EnviromentalAr.aspx
This document was prepared at an early stage of project development, before consideration by the EBRD Board of Directors. Details of a project may change following disclosure.
Environmental and Social Impact Assessments and ESIA summaries are produced by project sponsors, and the EBRD makes them available without any comment or implied endorsement. Any views expressed or statements made in the Environmental and Social Impact Assessment or the ESIA Summary do not necessarily reflect the views or opinions of the EBRD.
Last updated 25 June 2014