Corridor Vc in FBH - Part 3

Location:

Bosnia and Herzegovina

Project number:

49058

Business sector:

Transport

Notice type:

Public

ESIA disclosed:

21 Jul 2017

Status:

Disbursing

Approval date:

05 Sep 2018

Project description

Provision of a sovereign-guaranteed loan of up to EUR 205 million to the Motorways of the Federation of Bosnia and Herzegovina (the “Company” or the “FBHM”) to construct four new key sections of Corridor Vc with a total length of approximately 20.5 km (the “Project”).

The loan is composed of  two tranches as follows:

Tranche 1 in the amount of up to EUR 145 million to finance the construction of three motorway sections as follows:

i. EUR 50 million to finance the construction of Tunnel Ivan approximately 2 km in length;
ii. EUR 25 million to co-finance with the EIB Tunnel Zenica approximately 2.8 km in length; and
iii. EUR 70 million to co-finance with the EIB the construction of a motorways section from Poprikusa to Nemila, approximately 6.9 km in length.

Tranche 2 in the amount of up to EUR 60 million to finance the construction of a motorway section from the Mostar South Interchange to Tunnel Kvanj, approximately 9.2 km in length.

The availability of Tranche 2 will be at the EBRD’s sole discretion and will be subject to compliance with the Banks Environmental and Social Performance Requirements,  achievement of implementation and transition milestones to be determined after due diligence.

The Project is a follow on operation to the Bank’s previous projects for the construction of key motorway sections of Corridor Vc in Bosnia and Herzegovina (BiH) which connects Port of Ploce in Croatia with Budapest and is part of the Western Balkans Core Network.

Project objective

Support of BiH’s economic development and contribution to its regional and European integration by improving connectivity between its main cities and between BiH and neighbouring countries. 

ESIA disclosure package

Tranche 1

Environmental Impact Assessments: Further information

Non-Technical SummaryBosnian | English
 
Stakeholder Engagement Plan (SEP): Bosnian | English
 
Land Acquisition and Resettlement Plan – Section Tunnel Zenica (2017): Bosnian | English
 
Supplementary Biodiversity Assessment (July 2017): Bosnian | English
Biodiversity Management Plan (July 2017): Bosnian | English

Environmental and Social Action PlanBosnian | English

Land Acquisition and Resettlement FrameworkBosnian | English

Client siteBosnian | English

Tranche 2

1. Environmental and Social Impact Assessment (ESIA) including Environmental and Social Management Plan (ESMP)
2. Technical Annexes to ESIA
3. Environmental and Social Action Plan (ESAP)
4. Biodiversity Management Plan (BMP)
5. Non-Technical Summary (NTS)
6. Stakeholder Engagement Plan (SEP)
7. Land Acquisition and Livelihood Restoration Plan (LALRP)

Download the trache 2 package in zip format

Mostar South to Tunnel Kvanj Public Consultation Report Dec 2020

Full ESIA availability

Full ESIA documentation is available on the Client's website

Tranche 1

Tranche 2

Motorways of FBiH d.o.o., Sarajevo Office
Hamdije Kresevljakovica 19, 71000 Sarajevo
Contact person: Amir Fejzic, Head of Environmental and Social Team,
tel. +387 33 277 956

Motorways of  FBiH d.o.o. Mostar
Adema Buca 20, 88 000 Mostar
Contact person: Marijana Prkačin Goluža, Senior Assistant for Studies and Design
Tel. +387 36 512 352

Mostar City Administration
Hrvatskih Branitelja 2, 88000 Mostar 

And

EBRD, BiH
Contact
15th Floor, Tower B Unitic Towers
Fra Andela Zvizdovica 1, 71000 Sarajevo

During the active consultation period, the Client has disclosed the ESIA package in both the local and English language on the following website:
Local language | English language

and locally at:

Motorways of FBiH d.o.o., Sarajevo Office
Hamdije Kresevljakovica 19, 71000 Sarajevo
Contact person: Amir Fejzic, Head of Environmental and Social Team,
tel. +387 33 277 956

Motorways of  FBiH d.o.o. Mostar
Adema Buca 20, 88 000 Mostar
Contact person: Marijana Prkačin Goluža, Senior Assistant for Studies and Design
Tel. +387 36 512 352

Mostar City Administration
Hrvatskih Branitelja 2, 88000 Mostar 

And

EBRD, BiH
15th Floor, Tower B Unitic Towers
Fra Andela Zvizdovica 1
71000 Sarajevo, Bosnia and Herzegovina

And

Attention: Amir Fejzic
Head of Environmental and Social Team
tel. 00387 33 277 956
Motorways of FBiH
Postal Address: Hamdije Kresevljakovica 19, 71000 Sarajevo
Telephone: +387 33 277 956
E-mail address: info@jpautoceste.ba
www.jpautoceste.ba

General enquiries

Attention: Orhan Pasalic
Secretary of the Motorways of FBIH
Motorways of FBiH
Postal Address: Hamdije Kresevljakovica 19, 71000 Sarajevo
Telephone: +387 33 277 900
E-mail address: info@jpautoceste.ba 

This document was prepared at an early stage of project development, before consideration by the EBRD Board of Directors. Details of a project may change following disclosure.

Environmental and Social Impact Assessments and ESIA summaries are produced by project sponsors, and the EBRD makes them available without any comment or implied endorsement. Any views expressed or statements made in the Environmental and Social Impact Assessment or the ESIA Summary do not necessarily reflect the views or opinions of the EBRD.