Banie Wind Farm - extension

Location:

Poland

Project number:

47932

Business sector:

Notice type:

Private

ESIA disclosed:

29 Jan 2016

Status:

Complete

Approval date:

09 Dec 2015

Project description

After execution of the loan documentation for the 50MW Phase 1 of the Banie wind farm on the 18th of December 2015 with EBRD’s commitment of up to PLN 150 million (EUR 35 million), the Bank is currently considering increasing its commitment with an additional senior long-term loan of up to PLN 127 million (EUR 30 million) to finance the construction and operation of 56MW Phase 2 of the Banie wind farm, located in north western Poland (Phase 1 and Phase 2 jointly referred to as the "Project"). The construction of Phase 1 was finalized in December 2015, whereas the construction of Phase 2 started at the beginning of 2016 and is expected to be completed by mid-2016.

Both loans will be made available to Wiatromill SpK (the "Borrower") created to own, construct and operate the Banie wind farm. The Borrower is fully owned by Energix Renewable Energies Ltd. ("Energix" or the "Sponsor").

The combined Project will lead to the construction of 106MW of new renewable energy capacity in Poland. This is expected to generate over 187 thousand tonnes of CO2 savings per annum. In addition, the Project will also strengthen the private sector presence in the renewable energy sector in the country.

The Project is part of diversification for Poland energy generation source and support of renewable projects.

There is a Project Summary Document available for this project.

ESIA summary

Non-Technical Summary (NTS): English | Polish

Stakeholder Engagement Plan (SEP): English | Polish

Environmental and Social Action Plan (ESAP): English | Polish

Supplementary ESIA report: English | Polish

Full Polish EIA and Permits

Grievance Form | Formularz składania skarg i zażaleń

KOZ1_WIND_TURBINES | KOZ2_WIND_TURBINES

UG Banie - Decyzja Środowiskowa - GPZ Kozielice (ostateczna)

Decyzja środowiskowa Kozielice

Decyzja środowiskowa Kozielice (Rokity)

Decyzja środowiskowa (Tetyń)

Decyzja środowiskowa GPZ Nowe Czarnowo - Decyzja ostateczna

Decyzja Środowiskowa - GPZ Kozielice (ostateczna)

Ostateczna Decyzja Środowiskowa - FW Bielice

Raport ooś ZEW Bielice

Zał. nr 1 | Zał. nr 2 | Zał. nr 3 | Zał. nr 4 | Zał. nr 5 | Zał. nr 6 | Zał. nr 7 | Zał. nr 8a | Zał. nr 8b | Zał. nr 8c | Zał. nr 8d | Zał. nr 9 | Zał. nr 10 | Zał. nr 11a | Zał. nr 11b | Zał. nr 11c | Zał. nr 11d | Zał. nr 12a | Zał. nr 12b | Zał. nr 12c | Zał. nr 12d | Zał. nr 13 | Zał. nr 14 | Zał. nr 15 | Zał. nr 16 | Zał. nr 17

Full EIA availability

Full ESIA documentation is available locally at:

1.    Sponsor’s Local office

  • Hillel Barak, Operation Manger Wiatromill Sp. Z o. o. ul. Aleje Jerozolimskie 56c  00-803 Warszawa, Polska, email: Hillel@energix-group.com
     
  • Katarzyna Pysiak, Site Administration Manager Gryf Sp. z o.o. ul. Aleje Jerozolimskie 56c  00-803 Warszawa, Polska  Mobile: +48 728 856 535  email: biuroadmin@energix-group.com


2.    Local community

  • Gryfino Commune – Mr. Jacek Czaczyk, Department of Public Utilities, Housing and the Environment,
    tel. +91 416-20-11 (extension 214),
    1 Maja Street, 74-100 Gryfino
     
  • Kozielice Commune – Mr. Michał Ileczko, Specialist for Construction and Investments;
    tel: +91 561-11-41, Kozielice 73, 74-204 Kozielice
     
  • Bielice Commune – Mr. Zdzisław Badora, Specialist for Investments and Renovations, Spatial Planning and Road Construction; Tel: +91 56 44 235, (extension 21),
    34 Niepokalanej Street, 74 - 202 Bielice  
     
  • Banie Commune – Mr. Józef Gurdała, Investments Inspector, employee of the Banie Commune Seat.
    Tel: +91 416 63 81 (extension 37), 6 Skośna Street, 74-110 Banie


3. EBRD Resident Office in Warsaw

ul. Emillii Platter 52
Tel: 48 (22) 520 57 00
Contact: Mr Adarin Goralski
Email: gorlaska@ebrd.com
The ESIA package has also been released for public review by the project sponsor on the Project web site (link) – http://www.energix-group.com/Wind/).

Enquiries

General

Hillel Barak,
Operation Manger Wiatromill Sp. Z o. o.
ul. Aleje Jerozolimskie 56c  00-803 Warszawa, Polska,
email: Hillel@energix-group.com
 

 
 

This document was prepared at an early stage of project development, before consideration by the EBRD Board of Directors. Details of a project may change following disclosure.

Environmental and Social Impact Assessments and ESIA summaries are produced by project sponsors, and the EBRD makes them available without any comment or implied endorsement. Any views expressed or statements made in the Environmental and Social Impact Assessment or the ESIA Summary do not necessarily reflect the views or opinions of the EBRD.