Purpose of the Environmental and Social Impact Assessments
The proposed project consists of construction of a new 833 MW lignite fired unit at an existing 4,300 MWe lignite power plant operated by BOT Elektrownia Belchatow SA, accompanied by the associated investments i.e. modernisation of existing power units, additional flue gas desulphurisation (FGD) installations, new waste disposal system, a cooling tower for the new unit, etc.
The 833 MW power unit will be constructed on the basis of an EPC “turn-key” contract with Alstom consortium. The project sponsor is BOT Elektrownia Belchatow S.A., which belongs to the holding “BOT Górnictwo i Energetyka SA” (BOT GiE), a State owned power generating company.
The project represents a major step in upgrading existing generating assets in Poland to ensure that they meet EU environmental legislation post 2008, notably requirements of the EU Large Combustion Plant and IPPC directives. The project is also an integral part of Polish governmental energy security program.
There is a project summary document available for this project.
ESIA Summary
Executive Summary (English) (1MB - PDF)
Executive Summary (Polish) (2MB - PDF)
Full ESIA availability
Full ESIA documentation is available locally at:
EBRD Headquarters in London, environmentandsocial@ebrd.com
And
ELBIS Sp. z o.o.,
Rogowiec,
Belchatow.
Tel. +48(44) 735 33 40;
Contact: Mr Marek Wdowiak, Technical Director.
Website: http://www.elb2.pl/pl/konsultacje.html
And
BOT-Elektrownia Belchatow S.A.;
Rogowiec, 97-406 Bełchatów 5
Tel: +48 (44) 632-51-32;
Contact: Mr Miroslaw Niewiadomski, Environment Director
And
EBRD Resident Office Warsaw,
ul. Emillii Platter 52;
Tel: 48 (22) 520 58 26
Contact Lucyna Stanczak
Enquiries
Environmental enquiries
Mr Miroslaw Niewiadomski, Environment Director
BOT-Elektrownia Belchatow S.A.;
Rogowiec, 97-406 Bełchatów 5
Tel: +48 (44) 632-51-32;
General enquiries
Mr Marek Wdowiak, Technical Director
ELBIS Sp. z o.o.,
Rogowiec, Belchatow.
Tel. +48(44) 735 33 40;
This document was prepared at an early stage of project development, before consideration by the EBRD Board of Directors. Details of a project may change following disclosure.
Environmental and Social Impact Assessments and ESIA summaries are produced by project sponsors, and the EBRD makes them available without any comment or implied endorsement. Any views expressed or statements made in the Environmental and Social Impact Assessment or the ESIA Summary do not necessarily reflect the views or opinions of the EBRD.
Last updated 25 June 2014