Purpose of the Environmental and Social Impact Assessments
The Bank has been requested to finance the investment program of OGK-5’s Nevinnomysskaya GRES, a 1290 MWe gas-fired power plant located in Southern Russia. The Loan will finance the replacement of two inefficient gas-fired units (total capacity 310MW) with modern CCGT units (410MW) achieving enhanced environmental performance and adding 100 MW of generating capacity in this constrained region without increased utilisation of natural gas.
The project represents a major step in upgrading existing generating assets in Russia to ensure that they meet improved energy efficiency and higher environmental performance. The new project is part of a programme to improve the performance of existing plants in Russia and will result in lower carbon emission per MWe of generated electivity.
There is a project summary document available for this project.
ESIA Summary
Executive Summary (English) (1MB - PDF)
Executive Summary (Russian) (668KB - PDF)
Public Disclosure and Consultation Plan (English) (311KB - PDF)
Public Disclosure and Consultation Plan (Russian) (478KB - PDF)
Full ESIA availability
Full ESIA documentation is available locally at:
EBRD Headquarters in London, environmentandsocial@ebrd.com
And
The materials are available in hard copy at the following locations in Russia:
-
Nevinnomysskaya GRES Power Plant
Contact: Ms Irina Ushakova
Phone: (86554) 5-05-89, (86554) 5-01-11
Fax: (86554) 5-05-89
E-mail: Ushakova_ia@nevgres.ogk-5.com
-
OGK-5 Headquarters
10A/2 4th Setunsky proezd
Moscow 119136
Contact: Mr Vasily Zakharov
Phone: +7 (495) 380-02-30 ext. 5324
Fax: +7 (495) 380-02-39
E-mail: zakharov_vs@ogk-5.com
-
EBRD Resident Office in Moscow
6 Gasheka Street
Moscow 125047
Contact: Mr Vadim Dormidontov, Senior Banker
Phone: +7 (495) 787 1111
Fax +7 (495) 787 1122
E-mail: dormidov@ebrd.com
The EIA package and Executive Summary have also been released for public review by the project sponsor on its website:
http://www.ogk-5.com/ru/about_n/safety_n/
http://www.ogk-5.com/en/susta/envirpro/
and released locally in the following locations:
-
Nevinnomysskaya GRES Power Plant
Contact: Ms Irina Ushakova
Phone: (86554) 5-05-89, (86554) 5-01-11
Fax: (86554) 5-05-89
E-mail: Ushakova_ia@nevgres.ogk-5.com
-
Nevinnomyssk Public Library
B. Mira 16-a
Nevinnomyssk
Stavropol Krai, Russia
Additionally the executive summary is available on the EBRD internet sites at www.ebrd.com
Enquiries
Environmental enquiries:
-
At the power plant:
Nevinnomysskaya GRES Power Plant, Department of Ecology
Attn: Ms. Irina Ushakova
Telephone: (86554) 5-05-89, (86554) 5-01-11
Fax: (86554) 5-05-89
E-mail: Ushakova_ia@nevgres.ogk-5.com
-
At OGK- 5 Headquarters:
10A/2 4th Setunsky proezd
Moscow 119136
Attn: Mr Vasily Zakharov
Phone: +7 (495) 380-02-30 ext. 5324
Fax: +7 (495) 380-02-39
E-mail: zakharov_vs@ogk-5.com
This document was prepared at an early stage of project development, before consideration by the EBRD Board of Directors. Details of a project may change following disclosure.
Environmental and Social Impact Assessments and ESIA summaries are produced by project sponsors, and the EBRD makes them available without any comment or implied endorsement. Any views expressed or statements made in the Environmental and Social Impact Assessment or the ESIA Summary do not necessarily reflect the views or opinions of the EBRD.
Last updated 25 June 2014