Project summary document

Project name:Petrovax
Country:Russia
Project number:38257
Business sector:General manufacturing
Public/Private:Private
Environmental category:C
Board date:22 July 2008
Status:Signed
Date PSD disclosed:
Date PSD updated:
19 June 2008
Local language translation:Перевод на русский 
Date translation disclosed:26 June 2008
Help

Subscribe to PSD
email alerts

Related links
Russia homepage

Project description
and objectives:

The EBRD is considering an acquisition of a minority equity interest in NPO Petrovax Pharm LLC, a niche pharmaceutical company organized under the laws of Russian Federation.

The proceeds from the transaction will be used primarily in connection with (i) construction of an additional production line at the company's facility in Podolsk; (ii) research, development and commercialization of new products; and (iii) enhancement of the company's organizational structure and corporate governance standards.

Transition impact:

The transition impact in this Transaction will be achieved through:

  • Introduction of new products and technology – a portion of the transaction proceeds will be used to commercialize new pharmaceutical products currently in various stages of development.

  • Improvement of corporate governance standards – the Bank’s investment will support the company in its post-transaction corporate governance improvement strategy. The goals of this strategy will include bringing international corporate governance practices to the company.

 

The client:

NPO Petrovax Pharm is a niche pharmaceutical company involved in development and production of branded drugs and vaccines. The company’s main activities include development, registration, production and distribution of patented scientific inventions, primarily in the fields of immunology and viral diseases.

EBRD finance:

Up to RUB 664.2 million.

Total project cost:

Up to RUB 664.2 million.

Environmental impact:

The proposed project has been screened C/1. A range of environmental, health and safety audits and assessments have been undertaken as part of the Bank's due diligence. In December 2006, an environmental and social audit was conducted by independent consultants as part of the Bank's monitoring programme. Along with a series of environmental reports from the Company, the Bank's Environmental Specialist also visited the plant. All of the reports received, including the site visits, confirm that there are few, if any EHS risks associated with operation of the Company’s pharmaceutical plant in Podolsk. The plant has been built to a high standard and is operated in accordance with applicable national environmental, health and safety requirements, with GMP standards and in line with best international practice. An environmental action plan (EAP) has been developed and is being implemented in accordance with the Bank's requirements. The new production line to be financed with the Bank’s equity will have no significant adverse environmental impacts and will be constructed and operated to EU and best international standards.

Technical
cooperation:

None.

For consultant opportunities for projects financed by technical cooperation funds, visit procurement of consultants.

Company contact:

NPO Petrovax Pharm
Mr. Arkadiy V. Nekrasov, General Director

Tel: +7 (495) 984-2754
Fax: +7 (495) 984-2753

Email: NekrasovAV@petrovax.ru

EBRD contact:

Andrey Kalashnikov, Operation Leader: kalashna@ebrd.com

Business opportunities:

For business opportunities or procurement, contact the client company.

General enquiries:

EBRD project enquiries not related to procurement:
Tel: +44 20 7338 7168; Fax: +44 20 7338 7380
Email: projectenquiries@ebrd.com


Project Summary Documents are created before consideration by the EBRD Board of Directors. Details of a project may change following disclosure of a Project Summary Document. Project Summary Documents cannot be considered to represent official EBRD policy.
Terms and conditions Sitemap Feedback