EBRD homepage
About the EBRD
News & events
Publications
Countries & topics
Projects
 
Project summaries

Approved & signed

Case studies

Environmental documents

Evaluation
Apply for financing
Environment
Capital markets
Working together
 

 

Project summary document

Project name:Turceni Rehabilitation
Country:Romania
Project number:37696
Business sector:Power and Energy
Public/Private:Public
Environmental category:
Board date:9 September 2008
Status:Board approved, Pending signing
Date PSD disclosed:
Date PSD updated:
9 May 2008
5 August 2008
Local language translation:Traducere în limba română 
Date translation disclosed:30 May 2008
Help

Subscribe to PSD
email alerts

Related links
Romania homepage
Power and Energy homepage

Project description
and objectives:

The EBRD is considering arranging up to EUR 300 million in a syndicated loan for the rehabilitation and modernisation of units 3 and 6 of the Turceni power plant (CET) in Romania in order to:

1. Increase availability, efficiency and therewith the reliability of one of the most important power plants in Romania
2. Extend the units’ life time by at least 15 years,
3. Improve the environmental conditions for complying with the EU environmental directives
4. Implement a modern automation and control system, fulfilling the UCTE requirements.
The Project will be procured following EBRD’s Procurement Policies and Rules.

Transition impact:

This project will be the first non-sovereign long-term loan to a thermal power plant in Romania. It will demonstrate Romania’s extensive progress in market liberalisation by operating as a ring-fenced, standalone commercial entity competing for market share mainly as a merchant plant.

The client:

CET is the largest thermal power plant in Romania, and second in the merit order, generating roughly 10% of the domestic electricity consumption, with a total installed capacity of 2,310 MW and two open cast lignite mines.

EBRD finance:

EBRD is considering arranging up to EUR 300 million in a syndicated loan to commercial banks, using an A / B loan structure.

Total project cost:

Approximately EUR 500 million.

Environmental impact:

Project screening

Screened B/1. Following an Initial Environmental Examination (IEE) the project has been screened B/1 requiring an environmental audit of existing assets to assess current environmental status and an environmental analysis to ascertain whether the investment programme will allow the plant to meet EU environmental standard

Summary or Environmental and Social Due diligence undertaken and key findings

Following the IEE of the Bank an independent consultant was retained to undertake the environmental and social due diligence of the power plant complex and the associated lignite mines. The independent environmental and social due diligence confirmed that the project is structured to meet EU environmental standards and will result in significant environmental benefits in terms of reducing environmental emissions notably sulphur dioxide (SO2) and allow the plant to meet EU Large Combustion Plant standards and requirements of EU Accession Treaty.

The planned installation of Flue Gas Desulphurisation (FGD) on Units 3 to 6 and the rehabilitation and upgrade of the nitrous oxide (NOx) control for Units 4 and 5, will allow the plant to meet EU complaint emissions standards. The plant will meet among other requirements the more stringent NOx level emission post 2016 (200 mg/Nm3). This has been confirmed as part of the environmental and technical due diligence undertaken by the Bank.

The future transport of limestone to the plant may have some environmental and social impacts. The plant will continuously monitor the situation and assess alternative limestone suppliers and transport routes. A review will be made in 2013 to assess the impact of the adopted solution for limestone transport. The Company will use, among others, environmental and social criteria in the assessment of transport mode solution.

Continued environmental authorisation of the TPP is contingent on improvements being made to the site (the current IPPC permit expires in 2013). There are plans by the Company to bring about the extension of the Ash Pond at Valea Ceplea to allow it to take ash deposits through to 2012 and then it will be subject to a conservation process. The plant is investing in the development of a dense ash transport system and the development of a new ash pond adjacent to Ash Pond Number 2. Ash Pond Number 2 will be, in part, covered by the new development. This should allow better management of the transport water and create a landfill in-line with the EU Landfill Directive design parameters. It should reduce the risk of Valea Ceplea causing harm to the local environment.

Lignite mining operations are being carried out in a generally satisfactory manner but the management of surface waters in and adjacent to the mining pits and overburden dump are in need of improvement, particularly as this may lead to some instability of parts of the overburden dump.

Turceni needs to extend the mining areas both within its current exploitation licence area and into the wider area of the licensed reserve. There are a few legacy issues associated with previous resettlement and with acquiring land for the extension into the existing exploitation area (mainly to do with finance and appropriate incentives), with the main social issues likely to arise in ten to fifteen years time when development of the wider area is needed. These include issues relating to resettlement of households and the removal of a church and of a graveyard.

Clear and very complete guidance in relation to resettlement and compensation has been adopted in September 2005 for the mine sector and a Ministry of Economy and Commerce Order has been issued for approval in October 2005. This takes account of many previous experiences and provides formal templates for all aspects of the process, including inventories of land, crops, houses and other building, their construction and fittings, formal documentary agreements by asset category for transfer and for development of compensatory assets. The guidance improved the resettlement process. The Bank has reviewed this as part of the due diligence and provided additional guidance on the social and resettlement action plan to enable best practice to be met, including in the implementation of an appropriate grievance procedure.

The environmental and social action plan (ESAP) was agreed with the company, and it includes specific measures for implementing the investment programme at the company in terms of the planned modernization and attained LCPD and IPPC standards for the plant. In addition the ESAP addresses a number of managerial issues, such as environmental and health and safety management systems and social issues associated with the planned mine expansions, notably future resettlement plans

The Bank will monitoring the progress of implementation of the ESAP, and is investigating ways of helping the Company with the social and resettlement issues through technical assistance funding.

Technical
cooperation:

None.

For consultant opportunities for projects financed by technical cooperation funds, visit procurement of consultants.

EBRD contact:

Louis Borgo, Operation Leader: borgol@ebrd.com

Procurement or tendering
opportunities:

Visit EBRD Procurement
Enquiries: Tel: +44 20 7338 6794; Fax: +44 20 7338 7472, Email: procurement@ebrd.com

General enquiries:

EBRD project enquiries not related to procurement:
Tel: +44 20 7338 7168; Fax: +44 20 7338 7380
Email: projectenquiries@ebrd.com


Project Summary Documents are created before consideration by the EBRD Board of Directors. Details of a project may change following disclosure of a Project Summary Document. Project Summary Documents cannot be considered to represent official EBRD policy.
Terms and conditions Sitemap Feedback