Project name:Vez Svoghe mini hydro project
Country:Bulgaria
Project number:36032
Business sector:Power and Energy
Public/Private:Private
Environmental category:A
Board date:6 November 2007
Status:Signed
Date PSD disclosed:
Date PSD updated:
3 August 2007
29 November 2007
Local language translation:Българcки превод 
Date translation disclosed:9 October 2007
Help

Subscribe to PSD
email alerts

Related links
Bulgaria homepage
Power and Energy homepage
Vez Svoghe mini hydro project [Environmental Impact Assessment]
EBRD boosts support for renewable energy in Bulgaria [Press Release]

Project description
and objectives:

The proposed project is the construction of nine small hydro power plants (combined installed capacity of 25.7 MW) along a 33 km stretch of the middle section of the river Iskar. The plants will be built, owned and operated by Vez Svoghe Ltd – a special purpose company owned by Petrolvilla Bulgaria (90%) and the municipality of Svoge (10%). Petrolvilla Bulgaria is controlled by the Petrolvilla & Bortolotti S.p.A. group, which is primarily engaged in the provision of energy and energy-related products and services in northern Italy.

It should be noted that the first two of these nine plants are being partially financed under the Bulgarian Energy Efficiency and Renewable Energy Credit Line (www.beerecl.com) and that construction of these two plants has begun. As part of its financing of the remaining seven plants, EBRD will consider re-financing the first two plants. Therefore, all nine plants have been included into the project scope.

 

Transition impact:

The transition impact stems from supporting an investment in the Bulgarian renewable energy sector and the knowledge transfers arising from the project; Petrolvilla & Bortolotti has experience in building and operating technically similar small hydro power plants in Italy and in undertaking such projects in cooperation with municipalities. The latter aspect has the potential to help promote the development of public – private partnerships for smaller renewable energy projects. Finally, the Bank’s participation will ensure that the project is implemented in accordance with best environmental practices.

The client:

Vez Svoghe Ltd, supported by companies within the Petrolvilla & Bortolotti S.p.A. group.

EBRD finance:

EUR 54 million.

Total project cost:

Anticipated to be approximately EUR 81 million.

Environmental impact:

Screening category and justification

The project involves the development and operation of nine small hydro plants along the Iskar River in Bulgaria. The nature of development due to the potential cumulative impacts has been screened A/0 requiring an Environmental Impact Assessment (EIA) in accordance with EBRD’s Environmental Policy and Procedures. An external consultant has assisted Vez Svoghe in complementing the EIA which had been produced for the purposes of meeting both the national and the Bank’s environmental standards and procedures. The latter included the development of a Public Disclosure and Consultation Plan and an addendum to the Bulgarian EIA.

Due diligence undertaken and outcomes

An environmental due diligence was undertaken of the project by an international environmental consultant. This consisted of an assessment of environmental and social impacts associated with the construction and operation of the nine mini hydro plants and updating the Bulgarian EIA to take account of the Bank’s Environmental Policy requirements and best international practice.

Overall, the construction of small hydro power plants has the potential to lead to a net positive environmental impact through reduced greenhouse gas emissions and the diversification of energy sources away from nuclear and fossil fuels. To maximise the benefits of the investment, it is important to assess and mitigate the potential environmental risks. These include any potential detrimental impact on the following: adjacent nature protection areas; flora and fauna (in particular fish populations); visual impressions; river sediments; and cultural / architectural heritage. The environmental due diligence undertaken by the Bank revealed that there are no significant environmental issues associated with the investment, and the project is likely to improve the environmental condition of the river and increase the amenity value to the local communities. An Environmental Management Plan (“EMP”) has been developed as part of the EIA and this will be implemented by the Company.

Implementation requirements

  • The Company will be required to provide the Bank with an annual environmental report, including updates on the EMP, and notification on any material accidents of incidents.

  • The Company and its facilities will conduct its business with due regard to national and EU environmental regulations and standards.

  • The Company will arrange for periodic environmental audits and monitoring visits by Bank staff or appointed representatives, if and when deemed necessary.

 

 

There is an Environmental Impact Assesment available for this project.

Technical
cooperation:

Technical cooperation funding has been provided by the UK Department for International Development (DFID).

For consultant opportunities for projects financed by technical cooperation funds, visit procurement of consultants.

Company contact:

Plamen Dilkov, Managing Director
Vez Svoghe Ltd
7/B Stephan Karadja
1000 - Sofia, Bulgaria

Tel: +359.2.988.85.70
E-mail: plamen.dilkov@finenergy.it
Website: http://www.vezsvoghe.com/

 

EBRD contact:

Gunilla Nilsson, Operation Leader: nilssong@ebrd.com

Business opportunities:

For business opportunities or procurement, contact the client company.

General enquiries:

EBRD project enquiries not related to procurement:
Tel: +44 20 7338 7168; Fax: +44 20 7338 7380
Email: projectenquiries@ebrd.com


Project Summary Documents are created before consideration by the EBRD Board of Directors. Details of a project may change following disclosure of a Project Summary Document. Project Summary Documents cannot be considered to represent official EBRD policy.
Terms and conditions Sitemap Feedback