Project name:ZGOS - Zagreb Solid Waste Programme
Country:Croatia
Project number:33247
Business sector:Municipal and environmental infrastructure
Public/Private:Public
Environmental category:C
Board date:29 July 2003
Status:Signed
Date PSD disclosed:
Date PSD updated:
6 June 2003
24 October 2003
Help

Subscribe to PSD
email alerts

Related links
Croatia homepage
Municipal and environmental infrastructure homepage

Project description
and objectives:

The proposed project will refinance part of the existing Zagreb Solid Waste Programme (ZGOS) municipal loan and finance the completion of the last two landfill cells in order to comply with the EU standards and protect the nearby water sources of Zagreb.

Transition impact:

The loan for the new investment component and the re-financed amounts will not have a financial guarantee by the City. Instead, the loan will be supported by a Municipal Support Agreement relating to responsibilities of the City in relation to tariff policy, corporate governance and regulatory framework. This will make this transaction the first non-guaranteed direct public utility loan in Croatia by the Bank.

Further transition impact will be achieved through development and implementation of a Service and Operational contract between ZGOS and Zagreb, within the context also of a wider waste disposal strategy of the City.

The client:

ZGOS is a City-owned company in charge of operations of the Jakusevac landfill and rehabilitation of the existing dump into a sanitary landfill. Its main revenue source is fee payments for municipal solid waste disposal.

EBRD finance:

A/B loan of €40 million to ZGOS secured by a Municipal Support Agreement by the City of Zagreb.  EBRD loan of €23 million and B Loan of €17 million to be offered for syndication to other banks.  The A/B loan ratio and syndication level will be at same level as under previous municipal loan structure.

Total project cost:

€66.5 million.

Environmental impact:

The project was screened C/1. This project will finance the completion of two landfill cells as part of ongoing rehabilitation of the waste dump into a sanitary landfill under the Zagreb Solid Waste Management Project. There is no change to the scope of the rehabilitation project which will continue to bring significant environmental improvements to  the protection of groundwater sources of the City of Zagreb and to the adequate municipal solid waste disposal in a sanitary landfill in accordance with Croatian and EU environmental standards.

Detailed environmental due diligence, inclusive of an Environmental Impact Assessment, was carried out for the Zagreb Solid Waste Management Project.  It confirmed the ability of the project to bring the existing facilities into compliance with applicable Croatian and EU environmental standards.  It also assessed possible environmental liabilities associated with the previous waste management practices and suggested mitigation measures. The project sponsors carried out an extensive public consultation and environmental awareness programme.

Technical
cooperation:

Loan funded TC for the development and implementation of Service and Operational contract between ZGOS and the City of Zagreb.  No technical cooperation will be used in conjunction with this proposed transaction.

For consultant opportunities for projects financed by technical cooperation funds, visit procurement of consultants.

EBRD contact:

Davor Indic, Operation Leader: indicd@ebrd.com

Procurement or tendering
opportunities:

Visit EBRD Procurement
Enquiries: Tel: +44 20 7338 6794; Fax: +44 20 7338 7472, Email: procurement@ebrd.com

General enquiries:

EBRD project enquiries not related to procurement:
Tel: +44 20 7338 7168; Fax: +44 20 7338 7380
Email: projectenquiries@ebrd.com


Project Summary Documents are created before consideration by the EBRD Board of Directors. Details of a project may change following disclosure of a Project Summary Document. Project Summary Documents cannot be considered to represent official EBRD policy.
Terms and conditions Sitemap Feedback