Project summary document

Project name:EPS: Emergency Power Sector Reconstruction Loan
Country:Serbia
Project number:17829
Business sector:Power and Energy
Public/Private:Public
Environmental category:B
Board date:23 October 2001
Status:Signed
Date PSD disclosed:
Date PSD updated:
14 May 2001
25 October 2001
Help

Subscribe to PSD
email alerts

Related links
Serbia homepage
Power and Energy homepage

Project description
and objectives:

Proposed €100 million loan to Elektroprivreda Srbije to finance emergency rehabilitation and upgrades to thermal and hydro-generation plants, and to rehabilitate and upgrade transmission system.

The project aims to finance emergency rehabilitation and upgrades to thermal and hydro-generation plants, and to rehabilitate and upgrade the transmission system.

Transition impact:

The project would support the stabilisation of the electricity sector by improving reliability and increasing generation capacity as well as strengthening institutional and sector management.

The client:

Elektroprivreda Sribje (EPS) is a public enterprise of the Government of the Republic of Serbia. It is structured as a holding company with 24 operational subsidiary enterprises engaged in power generation, transmission and distribution, power system management and coal production. EPS is responsible for 95 per cent of the total power generation in the country, and with 63,000 employees, is the largest enterprise in the Federal Republic of Yugoslavia.

EBRD finance:

The loan of €100 million would finance priority investments starting in 2001-02. Donor grant funds from the European Agency for Reconstruction (EAR) and the World Bank will finance emergency maintenance and repairs on a parallel basis.

Total project cost:

€100 million

Environmental impact:

The EBRD's loan will be used for a number of rehabilitation/upgrade projects, including the overhaul of thermal and hydro-electric generation plants, the construction of new transmission sub-stations, upgrades to a transmission line and a new transmission line. Because of the variety of investments to be financed under this loan, a number of environmental issues need to be addressed. These include:

  • air emissions;
  • waste generation and disposal (mainly ash);
  • water usage and discharges;
  • storage, handling and disposal of hazardous substances (e.g. oils);
  • worker health and safety issues;
  • downstream water management;
  • impact on fisheries and river ecology;
  • loss of habitat and impact on surrounding areas (new developments);
  • visual impact (new transmission lines);
  • public information and consultation (particularly for new developments).

The project aims to improve the reliability and efficiency of the power system and will provide an opportunity to replace old equipment with more efficient technology, reducing losses and potential environmental impact (air emissions, oil leakages and spillages from sub-stations etc.). The project requires an Initial Environmental Examination (IEE) prior to allocating a screening category (or different categories for individual components).

Technical
cooperation:

None.

For consultant opportunities for projects financed by technical cooperation funds, visit procurement of consultants.

EBRD contact:

Harry Boyd-Carpenter, Operation Leader: boydcarh@ebrd.com

Procurement or tendering
opportunities:

Visit EBRD Procurement
Enquiries: Tel: +44 20 7338 6794; Fax: +44 20 7338 7472, Email: procurement@ebrd.com

General enquiries:

EBRD project enquiries not related to procurement:
Tel: +44 20 7338 7168; Fax: +44 20 7338 7380
Email: projectenquiries@ebrd.com


Project Summary Documents are created before consideration by the EBRD Board of Directors. Details of a project may change following disclosure of a Project Summary Document. Project Summary Documents cannot be considered to represent official EBRD policy.