Project name:Railway Development Project
Country:Ukraine
Project number:4080
Business sector:Transport
Public/Private:Public
Environmental category:B
Board date:5 October 1999
Status:Signed
Date PSD disclosed:
Date PSD updated:
22 February 1999
29 September 2001
Help

Subscribe to PSD
email alerts

Related links
Ukraine homepage
Transport homepage

Project description
and objectives:

The project will finance the purchase of track maintenance machinery and track improvement materials for the major rail corridor between L'viv and Kiev.

The project will assist UZ by:

  • improving maintenance on the Kyiv-L'viv rail line, UZ's main transport link to Europe;
  • reducing life-cycle costs of track by modernising UZ's maintenance methods; and
  • improving financial performance by aiding commercialisation measures.

Transition impact:

The investments will assist UZ to improve track maintenance. As a result UZ will be able to offer faster, more reliable rail freight transport services at lower cost; track maintenance costs will be reduced substantially. Policy reforms will promote improved financial performance, better management and commercialisation.

Phasing out the cross-subsidy from UZ's freight services to cover passenger losses will permit UZ to contain freight tariffs, making Ukraine's goods more competitive in the international market place. The project will help UZ to develop a commercialisation programme, to implement it through a rolling five-year business plan, and to plan for the commercialisation of UZ's non-core businesses, which could eventually lead to privatisation.

The client:

The client is the State Administration for Railway Transport of Ukraine (UZ), an entity wholly owned by the state.

EBRD finance:

Loan (sovereign guaranteed) of US$ 51.9 million (EUR 50 million) with a 15-year term.

Total project cost:

US$ 110.9 million (EUR 96.2 million)

Environmental impact:

The project was categorised as B/0, requiring an environmental analysis. The investment was preceded by a pre-investment study, which developed an Environmental Action Plan (EAP). This identified environmental issues that must be addressed during project implementation. During the operation and maintenance phase, adequate provision will be made for disposal of hazardous and non-hazardous solid wastes, water run-offs and possible increased noise along the railway corridors. As a condition of the effectiveness of the project, UZ will need to approve an EAP satisfactory to the Bank.

Technical
cooperation:

EU-Tacis (Bangkok Facility) has provided EUR 500,000 for project preparation and EUR 750,000 for project implementation. Further TC funding may be sought to assist UZ to improve its financial management and accounting systems.

For consultant opportunities for projects financed by technical cooperation funds, visit procurement of consultants.

EBRD contact:

Mark Magaletsky, Operation Leader: magaletm@ebrd.com

Procurement or tendering
opportunities:

Visit EBRD Procurement
Enquiries: Tel: +44 20 7338 6794; Fax: +44 20 7338 7472, Email: procurement@ebrd.com

General enquiries:

EBRD project enquiries not related to procurement:
Tel: +44 20 7338 7168; Fax: +44 20 7338 7380
Email: projectenquiries@ebrd.com


Project Summary Documents are created before consideration by the EBRD Board of Directors. Details of a project may change following disclosure of a Project Summary Document. Project Summary Documents cannot be considered to represent official EBRD policy.
Terms and conditions Sitemap Feedback