Project name:Tashkent Airport Rehabilitation
Country:Uzbekistan
Project number:1987
Business sector:Transport
Public/Private:Public
Environmental category:B
Board date:2 December 1997
Status:Signed
Date PSD disclosed:
Date PSD updated:
25 October 1996
18 December 1997
Help

Subscribe to PSD
email alerts

Related links
Uzbekistan homepage
Transport homepage
EUR36 million EBRD loan helped Tashkent Airport [Press Release]

Project description
and objectives:

Rehabilitation of the passenger terminal and improvements to taxiways and apron.

Operation objectives:

a. undertake urgently required rehabilitation of taxiways and related airside facilities;
b. complete modernisation of the passenger terminal building and associated services required to accommodate expected traffic levels over the next ten years;
c. assist in project implementation ensuring the transfer of procurement expertise and efficient project management skills.

Use of proceeds:

To finance the foreign exchange cost of the following items:

a. rehabilitation of taxiways and apron;
b. modernisation of passenger terminal;
c. consultancy assistance in project implementation.

Transition impact:

(i) Skill Transfer - The Bank will provide support to the Airport management and the civil aviation authorities for a project that will have investment implications not only for the aviation sector but also for Uzbekistan's involvement with foreign financing methods and procurement procedures (consultancy assistance to be provided to the Project Implementation Unit).

(ii) Competition/Market Structure - The project will ensure implementation of market-oriented management and operational practices at the Airport.

(iii) Institutional Functioning - Sector reorganisation and transformation of existing institutions into a network of commercially oriented, financially self-sufficient companies constitutes a pre-condition of project approval by KfW's and EBRD's respective managements.

The client:

Tashkent Airport Enterprise - an independent airport company managing the airport operations and responsible for provision of airport services at the Tashkent Airport.

EBRD finance:

US$ 48 million loan (ECU 38 million).

Total project cost:

US$ 51.3 million (ECU 40.7 million).

Environmental impact:

This project, screened B/0, involves a complete modernisation of the passenger terminal building and rehabilitation of runways at Tashkent Airport. An environmental analysis is currently being undertaken by independent consultants which will involve the identification and assessment of all significant environmental effects associated with the rehabilitation plans for the runways, taxiways and apron, including potential for increased ground and surface water pollution caused by runoff during construction and from increased use of the infrastructure. In addition, noise/air pollution from extra traffic movements and ecological impact on existing and proposed land use in the vicinity of the airport will be analysed. The final report will include an environmental, health and safety action plan to be carried out within the project to ensure compliance with relevant national and international standards and Bank requirements.

Technical
cooperation:

None.

For consultant opportunities for projects financed by technical cooperation funds, visit procurement of consultants.

EBRD contact:

Dilshod Akhundjanov, Operation Leader: akhundjd@ebrd.com

Procurement or tendering
opportunities:

Visit EBRD Procurement
Enquiries: Tel: +44 20 7338 6794; Fax: +44 20 7338 7472, Email: procurement@ebrd.com

General enquiries:

EBRD project enquiries not related to procurement:
Tel: +44 20 7338 7168; Fax: +44 20 7338 7380
Email: projectenquiries@ebrd.com


Project Summary Documents are created before consideration by the EBRD Board of Directors. Details of a project may change following disclosure of a Project Summary Document. Project Summary Documents cannot be considered to represent official EBRD policy.
Terms and conditions Sitemap Feedback